Hyde Housing Association Limited (202017270)
REPORT
COMPLAINT 202017270
Hyde Housing Association Limited
12 June 2023
Our approach
The Housing Ombudsman’s approach to investigating and determining complaints is to decide what is fair in all the circumstances of the case. This is set out in the Housing Act 1996 and the Housing Ombudsman Scheme (the Scheme). The Ombudsman considers the evidence and looks to see if there has been any ‘maladministration’, for example whether the landlord has failed to keep to the law, followed proper procedure, followed good practice or behaved in a reasonable and competent manner.
Both the resident and the landlord have submitted information to the Ombudsman and this has been carefully considered. Their accounts of what has happened are summarised below. This report is not an exhaustive description of all the events that have occurred in relation to this case, but an outline of the key issues as a background to the investigation’s findings.
The complaint
- The landlord’s response to reports of trees damaging the fencing and shed.
- The landlord’s handling of repairs to the property.
- The standard of the service provided by the landlord.
Background and summary of events
The landlord does not have any recorded vulnerabilities listed for the resident.
Section 10(g) of the tenancy agreement states the landlord is responsible for boundary walls and fences.
Section 10(h) of the tenancy agreement states the landlord is responsible for internal walls, floors and ceilings.
The landlord’s repair policy is on its website and states it will:
- Install communal and boundary fencing to public or adjoining private land (not dividing fences between homes).
- Remove dead, diseased or dangerous trees in communal back gardens and in street properties, after assessment.
Summary of Events
- The tree surgeon had visited on 10 April 2021.
- The landlord and the council were denying responsibility for three of the seven trees that needed removing.
- Her garden backs onto public land, her shed had been destroyed by hanging Russian vines from the trees and once it collapsed she would have had no privacy.
- The situation had been going on for almost one year.
- She wanted confirmation of who was denying ownership of the trees
.
- After the report regarding the fence was made in August 2020 a contractor attended the same month and advised the fence could not be replaced until the trees and Russian vine had been attended to. The resident was told it was the responsibility of the council to do this by the contractor.
- The council attended and removed vegetation they were responsible for and said what was left was the responsibility of the landlord.
- The resident had made numerous phone calls and emails to the landlord and was contacted by its surveyor in March 2021 who sent tree surgeons to the resident’s home.
- The resident was advised by the landlords surveyor there were seven Ash trees and Russian vine that needed attending to. The resident sent the surveyor evidence from the council of the landlord’s responsibility and heard nothing further.
- The operative who attended the residents property on 11 May 2021 to apply sealant around the bath had advised the resident that where there was a gap due to missing tiles, water was escaping causing damage to the residents utility room ceiling and the resident was concerned about the ceiling bowing and being damaged.
The stage one response stated it could only:
- It could have done more to complete the repairs quicker for the resident and upheld the complaint.
- It offered £250 as an apology for the service the resident experienced.
- It committed to:
Investigate the trees in the garden and resolve the issue.
Repair/replace the fencing that backed onto the communal area once the trees had been attended to.
Attend to the ceiling in the utility room under the bathroom.
Replace the tiling in the bathroom.
Complete repairs to the front room window.
- The front room window to be repaired was not on the contractor’s list of works.
- The contractor would not approve the work to be carried out on the bathroom tiles.
- She had been told the ceiling repair had been completed but the ceiling was only painted and was still bowed.
- Trees had not been tended to and previously good parts of the fence were being destroyed. The resident asked who would pay for the cost of the shed to be replaced.
- The contractor had told the resident the landlord would not give permission for the works to be completed and the resident could not reach the landlord’s surveyor on the phone.
The landlord acknowledged the escalation request the same day.
On 1 November 2021, the resident emailed the landlord to ask for an update on the trees.
The landlord issued its stage two response on 4 November 2021. In the response the landlord stated:
- It did not manage the progress of the repairs effectively and failed to communicate with any reassurance to the resident how it was going to put things right.
- It was aware the resident had had six visits from various tradesman to complete the tiling works and once completed the resident was not happy with the quality of the completed work which it agreed was very poor. It had arranged for the works to be completed by a competent tiler on 5 November 2021.
- Following the redecoration to the bathroom ceiling on 20 July 2021 the resident was not happy with the landlord’s decision not to fix the ceiling where it had bowed due to the previous damage. It had reviewed its response and changed its decision. It competed replaster and repainting works on the ceiling which were completed by 30 October 2021.
- The work on the trees had been delayed due to the time it took to establish which trees were the responsibility of the landlord and this was due to communication between the landlord and the council. It informed the resident its tree surgeon had no capacity to survey the trees until early November 2021 and once that was completed they would know more about what would need to be done.
- It acknowledged it had failed to respond to the resident in line with its internal complaint process and apologised to the resident.
- It offered to increase the residents compensation offer from £250 to £450.
The landlord confirmed that the tree works were completed on 4 May 2022.
Assessment and findings
The landlord’s handling of tree repairs.
The landlord has provided a repairs log showing that survey requests of the trees were raised on 8 April 2021 however no other repairs are logged regarding the trees.
The landlord’s handling of the property repairs.
The landlords handling of the complaint
Determination (decision)
Reasons
Orders and recommendations
Orders
Within four weeks of the date of this report the landlord is to pay the resident £750 consisting of:
- £350 for the delay in responding to and completing the tree works.
- £200 for the handling of the repair works to the tiles in the bathroom and ceiling in the utility room.
- £200 for the its delays in the complaint handling.